SUMMARY

Slurry

As part of Vallejo's preventative maintenance program, 105 streets were slurry-sealed throughout the City. Slurry seal is an asphaltic and polymer-based emulsion applied to existing asphalt street pavements that are not yet significantly deteriorated, in order to prevent further degradation caused by the sun's radiation, intrusion of rain water, and oxidation. Slurry sealing is one of the most cost effective methods of prolonging the service life of street pavement over time.

Cost: $850M Engineer's Estimate
$942K Construction Contract

Status: Complete

SCHEDULE

  • August 24, 2012 - Advertise for Bids
  • September 6, 2012 - Bid Opening
  • September 18, 2012 - Award Construction Contract
  • October 10, 2012 - Notice to Proceed
  • November 13, 2012 - Citywide Slurry Seal Complete, Winter Suspension Begins
  • April 9, 2013 - Winter Suspension Ends, Hiddenbrooke Slurry Seal Begins
  • May 20, 2013 - Work Complete

PROJECT DOCUMENTS

Go to the following location to access project files.

If you have questions contact Josh Sanchez, Project Manager (707) 648-5229, [email protected].